Gantt chart type project plan

Welcome to PocketShip.net! This bulletin board is for builders of the Chesapeake Light Craft-John C. Harris "PocketShip" design, a 15-foot micro cruiser sailboat built from a kit or plans.

For more information on PocketShip, click here: http://www.clcboats.com/pocketship

This site gathers PocketShip builders in one place. Here you can share photos, tips, questions, and---eventually---your sailing adventures in PocketShip! CLC will also post design updates and tips here as they come up.

We'll try to knock down spam as quickly as possible.

Moderator: John C. Harris

Forum rules
Spam or commercial posts will be deleted.
This is a civil forum: no flames or drunken tirades.
Please stay on-topic.
PocketShip's Web Page: http://www.clcboats.com/pocketship
If you need CLC customer service: http://www.clcboats.com/forms/contact_us.html
We'll try to delete spam as soon as it appears.

Gantt chart type project plan

Postby wmewheel on Tue May 19, 2020 11:52 am

Has anyone (and I it has to be yes) put together a gantt type of project plan for the boat build from a kit? All the tasks that are precedents or jobs that can be done in parallel identified?
I'd rather not re-create this wheel. Thanks, Mark
Want to make sure that I'm doing all the epoxy sets in parallel whenever possible.
wmewheel
 
Posts: 18
Joined: Mon Jan 09, 2012 10:31 am

Re: Gantt chart type project plan

Postby craig on Tue May 19, 2020 2:30 pm

Not that I'm aware, at least not on this forum or the blogs I've seen.

You could do the rudder in parallel, and the spars. The stuff on the hull itself though is more or less built to fit, so you wouldn't want to build the companionway too far ahead without being sure it fits to the roof.
Titania, launched January 2015
craig
 
Posts: 284
Joined: Fri Feb 21, 2014 1:04 pm
Location: Chapel Hill, NC

Re: Gantt chart type project plan

Postby JonLee on Wed May 20, 2020 10:33 pm

(Nerd Alert) I've done it for a Jimmy Skiff II that we (a team of four) build in 2.5 days at the Wooden Boat Festival in Port Townsend last year. It was necessary to figure out what the critical path was to enable us to complete the boat on time, how to divide up the labor amongst the team, as well as plan out when lunches could be and what could be done as other things dried. I did it in Excel and printed out a huge copy for reference during the build (I forget how many sheets of paper, but I remember taping them all carefully together while waiting for the ferry over). Super helpful if you are building a boat in 2.5 days, but a huge pain to set up and populate.
JonLee
 
Posts: 195
Joined: Tue Oct 19, 2010 10:02 am